Title
ASEC Development and Construction Corp. vs. Toyota Alabang, Inc.
Case
G.R. No. 243477-78
Decision Date
Apr 27, 2022
Dispute over glass specifications in Toyota Alabang Showroom Project led to conflicting arbitral awards; Supreme Court reinstated first award, emphasizing finality of arbitration and co-equal tribunals.
A

Case Summary (G.R. No. 243477-78)

Applicable Law

This case is governed by the provisions of the 1987 Philippine Constitution and applicable Philippine laws, particularly Executive Order No. 1008, known as the Construction Industry Arbitration Law, and its implementing rules, which dictate the governance of arbitration processes within the construction industry.

Background of the Case

In 2013, ASEC Development submitted a bid for the construction project amounting to P399,000,000.00, which was accepted, and a contract was signed on September 19, 2013. Disputes arose regarding the specifications of materials to be used, specifically concerning tempered glass versus Low-E glass for the showroom's doors and windows, which led to misunderstandings over contract compliance and cost deductions.

Initial Arbitration and First Arbitral Award

Disputes over the correct deductibles for the glass works led ASEC Development to file for arbitration with the Construction Industry Arbitration Commission (CIAC), resulting in the First Arbitral Award rendered on June 30, 2014. The tribunal upheld ASEC Development’s claim, determining that only P32,540,329.98 should be deducted from the contract price, reflecting only the costs associated with tempered glass, sun baffles, and canopies, as opposed to the higher amounts claimed by Toyota.

Respondent’s Appeal and Termination of Contract

Following the First Arbitral Award, Toyota filed a petition for review with the Court of Appeals and simultaneously issued a Notice of Termination to ASEC Development due to alleged delays and contract non-compliance. ASEC Development contended that termination was unfounded and initiated a second arbitration seeking payment for outstanding progress billings valued at P78,968,626.83.

Second Arbitral Award and Resolutions

The second arbitration resulted in a Final Award issued on October 5, 2015, which contradicted the First Arbitral Award and allowed deductions of P51,022,240.00 from the original contract. It deemed ASEC Development as having failed to achieve practical completion and validated Toyota's termination of the contract, which also entailed claims for liquidated damages.

Court of Appeals’ Findings

The Court of Appeals, in its October 10, 2018, decision, set aside the First Arbitral Award while affirming the Second Arbitral Award, rationalizing that ASEC was liable for using the incorrect glass specification and thus, allowed for higher deductions against its total claim.

Supreme Court Review

ASEC Development contested the findings of the Court of Appeals, asserting that it violated the principle of respecting the finality of arbitral awards, and claimed that the Second Arbitral Award improperly overridden the First. The Supreme Court noted that arbitral awards are final and binding, reiterating that vacatur of awards should only occur under specific and limited circumstances.

Decision of the Supreme Court

The Supreme Court identified that the disputes raised by ASEC Development should not have led to an overriding ruling by the second arbitral tribunal, as the two arbitral bodies are intended to function independently without the ability to negate one another's awards. T

...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.