Title
Arwood Industries Inc. vs. D.M. Consunji Inc.
Case
G.R. No. 142277
Decision Date
Dec 11, 2002
Arwood Industries failed to pay D.M. Consunji, Inc. P962,434.78 for completed construction. Courts upheld 2% monthly interest as per contract but deleted attorney’s fees due to lack of justification.
Font Size:

Case Summary (G.R. No. 142277)

Case Overview

This case involves a petition for review concerning a contractual dispute between Arwood Industries, Inc. (Petitioner) and D.M. Consunji, Inc. (Respondent) regarding the imposition of interest on a balance of the contract price. The Court of Appeals affirmed the Regional Trial Court’s decision, which awarded the Respondent a monetary claim, including interest and damages.

Background of the Case

  • Contract Parties: Arwood Industries, Inc. (Owner) and D.M. Consunji, Inc. (Contractor).
  • Contract Date: February 6, 1989.
  • Project: Construction of Westwood Condominium located in San Juan, Metro Manila.
  • Contract Price: ₱20,800,000.00.
  • Unpaid Amount: ₱962,434.78 remained unpaid after project completion.

Legal Issues Presented

  • Core Issue: The propriety of the 2% monthly interest imposed on the unpaid balance of ₱962,434.78.

Trial Court Decision

  • Judgment: The trial court ordered Petitioner to pay:
    • ₱962,434.78 (balance of contract price) with 2% interest per month from November 1990 until payment.
    • ₱150,000.00 as attorney's fees.
    • Costs of suit.

Court of Appeals Decision

  • Affirmation with Modification: The Court of Appeals upheld the trial court's decision but removed the award of attorney's fees, citing lack of justification in the body of the decision.

Relevant Provisions from the Agreement

  • Article 6.03: States that if the Owner delays payment beyond 15 calendar days, the Contractor can either suspend work or continue work with an interest charge of 2% per month on the due amount.

Key Legal Principles

  • Interest on Unpaid Amount:
    • The court confirmed that the imposition of 2% monthly interest is valid due to the explicit provision in the Agreement.
    • Interest serves as compensation for damages incurred by the Contractor due to delayed payment.

Arguments by the Petitioner

  • Claimed that the interest provision applied only to monthly progress billings and not to the final balance.
  • Argued that the trial court's decision did not explicitly mention the interest in the dispositive portion, and hence, should not apply.
  • Contended that the pre-trial order did not include interest as an issue for resolution.

Court Rulings and Justifications

  • The court ruled that the Agreement’s provisions are binding, and the existence of the 2% interest clause cannot be disregarded.
  • The Petitioner was deemed liable for damages due to their failure to pay on time, which justifies the interest.
  • The court dismissed the notion that the interest provision was not applicable to the final balance, asserting that all payments are part of the contract price.

Key Takeaways

  • The court upheld the validity of the 2% monthly interest based on the contractual Agreement.
  • The absence of an objection to the contents of the Agreement during trial precluded the Petitioner from contesting the interest provision.
  • The ruling reinforces the princip

...continue reading

Analyze Cases Smarter, Faster
Jur is an AI-powered legal research tool in the Philippines with case digests and full jurisprudence. AI summaries highlight key points but may miss details, so always refer to the full text for accuracy.