Title
American Home Insurance Co. of New York vs. F.F. Cruz and Co., Inc.
Case
G.R. No. 174926
Decision Date
Aug 10, 2011
A dredging subcontractor abandoned a project, failing to repay a P2.2M advance. The surety bond issuer was held liable for the unpaid amount, as the bond guaranteed repayment, not project completion.

Case Summary (G.R. No. 174926)

Background of the Case

In June 1990, the PPA awarded a contract to F.F. Cruz for the dredging of the entrance channel and harbor basin of the Cebu International Port. Subsequently, G. Reyes entered into a Sub-Contract Agreement with F.F. Cruz, wherein G. Reyes was to complete 50% of the estimated dredging volume. An essential component of this subcontract was the requirement for G. Reyes to secure a performance bond from an accredited surety company, which was ultimately provided by American Home.

Indemnity and Advance Payment

American Home issued a surety bond in the amount of P2.2 million to guarantee G. Reyes's obligations under the subcontract, particularly ensuring the repayment of an advance payment made by F.F. Cruz to G. Reyes. To secure this bond, Genaro Reyes and his wife executed an Indemnity Agreement with American Home, agreeing to indemnify the insurer for any damages or losses incurred as a result of the suretyship.

Project Abandonment and Dispute

In the course of the project, G. Reyes encountered issues related to siltation, which it claimed hindered its ability to complete the dredging work as stipulated. After failing to comply with contract requirements and ultimately abandoning the project, G. Reyes informed F.F. Cruz that it could no longer continue, prompting F.F. Cruz to take over the unfinished work. Consequently, F.F. Cruz demanded payment from American Home under the surety bond due to G. Reyes's failure to fulfill its subcontracting obligations.

Legal Proceedings

American Home filed a complaint against G. Reyes and its representatives for the amount of the bond plus associated costs, while G. Reyes countered that they had not breached their obligations. The Regional Trial Court of Makati ruled in favor of F.F. Cruz and held American Home liable for the bond amount. This decision was appealed to the Court of Appeals, which affirmed the lower court's ruling.

Court of Appeals Decision

The Court of Appeals found that G. Reyes failed to meet its obligations under the subcontract, having completed significantly less dredging than agreed upon. The appellate court rejected G. Reyes's arguments regarding force majeure, finding no evidence to support claims of heavy siltation adversely affecting the project. Thus, American Home was rendered liable for the payment due to the non-fulfillment of G. Reyes's obligations.

Supreme Court Review

On further review, American Home raised several arguments challenging the appellate court's interpretation of the bond as a performance bond rather than merely a guarantee for advance payments. However, the Supr

...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster—building context before diving into full texts.