Title
Shinryo Company, Inc. vs. RRN, Inc.
Case
G.R. No. 172525
Decision Date
Oct 20, 2010
Shinryo and RRN disputed unpaid sub-contract balances, variation costs, and equipment fees. CIAC ruled for RRN; CA and SC affirmed, citing finality of factual findings and lack of unjust enrichment.

Case Digest (G.R. No. 172525)
Expanded Legal Reasoning Model

Facts:

  • Parties and Legal Background
    • Petitioner: Shinryo (Philippines) Company, Inc. – a domestic corporation organized under Philippine laws.
    • Respondent: RRN Incorporated – also a domestic corporation organized under Philippine laws.
  • Underlying Dispute and Claims
    • Respondent filed a claim for arbitration before the Construction Industry Arbitration Commission (CIAC) for recovery of an unpaid account totaling P5,275,184.17, plus legal interest of P442,014.73.
    • Petitioner counterclaimed for alleged overpayment amounting to P2,512,997.96.
  • Contractual Agreements and Project Details
    • The parties executed an Agreement and Conditions of Sub-contract in June 1996 establishing the framework for their commercial relationship.
    • On June 11, 2002, and June 14, 2002, the parties entered into an additional agreement for the “Supply of Manpower, Tools/Equipment, Consumables for the Electrical Works-Power and Equipment Supply, Bus Duct Installation” covering the Phillip Morris Greenfield Project with purchase orders amounting to a total of P25,000,000.00.
    • The agreement also contemplated that respondent would perform variation orders related to the project.
  • Performance, Payments, and Financial Difficulties
    • Petitioner supplied manpower and other services chargeable against the project under the contractual terms.
    • Financial difficulties on the part of respondent hindered the completion of the full scope of works.
    • Petitioner paid respondent a total amount of P26,547,624.76 over the course of the project.
  • Communications and Pre-Arbitration Events
    • June 25, 2003 – Respondent (through its former counsel) demanded payment of the unpaid balance of P5,275,184.17, while petitioner claimed material back charges amounting to P4,063,633.43.
    • September 26, 2003 – Respondent acknowledged only P2,371,895.33 as valid material back charges.
    • October 16, 2003 and January 8, 2004 – Additional correspondence from respondent indicated intentions to settle differences, including equipment rental charges and use of scaffolding.
    • August 12, 2004 – Petitioner sent a letter denying any unpaid account and noting failed settlement negotiations.
  • Arbitration Proceedings and Terms of Reference
    • The dispute was submitted to arbitration before the CIAC where the parties agreed on Terms of Reference resolving eight distinct issues (including evaluation of variation cost, equipment rental fee, evaluation of materials supplied, remaining works value, validation of inventoried excess materials, overpayment claim, interest entitlement, and allocation of arbitration costs).
    • The CIAC rendered an award in favor of respondent, ordering payment of an unpaid account of P3,728,960.54 plus legal interest and designated arbitration costs of P104,333.82.
  • Appellate Proceedings
    • February 22, 2006 – The Court of Appeals (CA) promulgated a decision affirming the CIAC’s award.
    • April 26, 2006 – Petitioner’s motion for reconsideration before the CA was denied.
  • Petition for Review on Certiorari and Alleged Errors
    • Petitioner alleged that the CA committed reversible errors by:
      • Denying its claim for manlift equipment rental of P511,000.00, despite evidence that respondent used and benefited from the equipment.
      • Deciding a question of substance not aligned with established law or Supreme Court precedents.
      • Erroneously affirming the CIAC award on inventoried materials and disregarding evidence that respondent admitted deductions on material supply.
      • Ignoring the subcontract provision allowing payment of the actual costs incurred by petitioner to complete the remaining works.
      • Overlooking evidence of actual cost incurred by petitioner in completing the unfinished portion of the works.
      • Affirming award for interests and arbitration costs in favor of respondent.
  • Supreme Court’s Review and Contextual Considerations
    • The Supreme Court’s decision reaffirmed the finality of the factual findings of the CIAC and upheld the CA’s ruling after considering relevant jurisprudence on the finality of arbitral awards.
    • The Court emphasized that the issues raised were primarily factual and that a reexamination or recalibration of the evidence is not proper, given the specialized nature of construction arbitration.
    • The petition was found to lack merit and failed to create sufficient grounds for reversing the established awards.

Issues:

  • Whether respondent’s free use of the manlift equipment, which allegedly benefited it, entitled petitioner to claim manlift equipment rental of P511,000.00.
  • Whether the Court of Appeals erred in rejecting petitioner’s claim for reimbursement based on costs associated with inventoried excess materials.
  • Whether the CA improperly disregarded the subcontract provision that allowed for payment of the actual costs incurred by petitioner in completing the remaining works once respondent failed to complete the work.
  • Whether the CA committed reversible error by ignoring evidence of the actual costs incurred by petitioner in finishing the remaining works.
  • Whether the CA erred in affirming the CIAC’s award on legal interest and arbitration costs in favor of respondent.
  • Whether the CIAC and the CA exceeded their proper role by engaging in recalibration of factual evidence, which in turn amounted to a re-litigation of the evidentiary record already presented before the arbitral tribunal.

Ruling:

  • (Subscriber-Only)

Ratio:

  • (Subscriber-Only)

Doctrine:

  • (Subscriber-Only)

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster—building context before diving into full texts.