Title
Rivelisa Realty, Inc. vs. 1st Sta. Clara Builders Corp.
Case
G.R. No. 189618
Decision Date
Jan 15, 2014
Rivelisa Realty and First Sta. Clara's JVA dispute over subdivision development; SC upheld CA ruling, awarding P3M reimbursement under quantum meruit.

Case Digest (G.R. No. 189618)
Expanded Legal Reasoning Model

Facts:

  • Contractual Agreement and Project Implementation
    • On January 25, 1995, Rivelisa Realty, Inc. (Rivelisa Realty) and First Sta. Clara Builders Corporation (First Sta. Clara) entered into a Joint Venture Agreement (JVA) for the construction and development of a residential subdivision in Cabanatuan City.
    • Under the JVA terms, First Sta. Clara was tasked to undertake horizontal development of the remaining 69% undeveloped portion of the project, with a completion period of twelve (12) months from signing.
    • Upon completion, 60% of the subdivided lots would be transferred to First Sta. Clara.
    • Since 31% of the project had been developed previously by Rivelisa Realty with an assessed value of ₱10,000,000.00, First Sta. Clara was to initially expend the equivalent amount before claiming funds from pre-sale of the initially developed lots.
    • Additional works not included originally in the JVA were to be borne 40% by Rivelisa Realty and 60% by First Sta. Clara.
  • Project Difficulties and Disputes
    • First Sta. Clara hired a subcontractor for horizontal development, including riprap and road embankment elevation.
    • After two months, First Sta. Clara ran out of funds, forcing Rivelisa Realty to advance part of the subcontractor’s payments.
    • First Sta. Clara expressed intention to withdraw from the JVA when Rivelisa Realty refused to provide further funding until at least 60% of the project was completed.
    • Rivelisa Realty, in a letter dated August 24, 1995, agreed to release First Sta. Clara from the JVA, estimating actual accomplishment at ₱4,000,000.00, including subcontractor payments and cash advances.
    • First Sta. Clara claimed a higher valuation of accomplished works at ₱4,578,142.10 and sought reimbursement of ₱3,000,000.00 after deducting cash advances and subcontractor fees.
    • After correspondence, Rivelisa Realty agreed to reimburse ₱3,000,000.00, emphasizing this amount was beyond its contractual obligations under the JVA.
    • Payment was not made despite demands, prompting First Sta. Clara to file a complaint for rescission of the JVA alleging breach of contract and damages due to delay.
  • Regional Trial Court Proceedings
    • The RTC ruled in favor of Rivelisa Realty, dismissing First Sta. Clara’s complaint and ordering First Sta. Clara to pay Rivelisa Realty damages and attorney’s fees for counterclaims.
    • The RTC found that First Sta. Clara failed to meet essential conditions of the JVA, including completing the development within 12 months, spending the initial ₱10,000,000.00, and accomplishing 60% of the work.
    • Since First Sta. Clara ceased work prematurely due to lack of funds, it was the party who first violated the agreement.
  • Court of Appeals Proceedings
    • On appeal, the CA reversed the RTC, finding Rivelisa Realty liable to compensate First Sta. Clara for actual work done amounting to ₱3,000,000.00 after deducting advances and costs.
    • The CA held that the JVA was terminated by mutual assent, freeing First Sta. Clara from further obligations.
    • Rivelisa Realty filed a motion for extension of time to file a motion for reconsideration beyond the 15-day reglementary period.
    • The CA denied the motion for extension and subsequently denied the motion for reconsideration as late-filed.
  • Petition to the Supreme Court
    • Rivelisa Realty filed a petition for review on certiorari questioning the non-extendible time for filing a motion for reconsideration and the entitlement of First Sta. Clara to compensation for the completed works.

Issues:

  • Whether the Court of Appeals erred in ruling that the 15-day reglementary period for filing a motion for reconsideration is non-extendible.
  • Whether First Sta. Clara is entitled to compensation for the development works performed on the project despite the termination of the Joint Venture Agreement.

Ruling:

  • (Subscriber-Only)

Ratio:

  • (Subscriber-Only)

Doctrine:

  • (Subscriber-Only)

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster—building context before diving into full texts.