Title
Philrock, Inc. vs. Construction Industry Arbitration Commission
Case
G.R. No. 132848-49
Decision Date
Jun 26, 2001
The Cid spouses sued Philrock for damages due to substandard concrete; arbitration resumed despite jurisdictional disputes, affirming awards except nominal damages.

Case Digest (G.R. No. 132848-49)
Expanded Legal Reasoning Model

Facts:

  • Background and Parties
    • The dispute arises from a construction contract involving Petitioner Philrock, Inc. and Respondents, the Cid spouses.
    • The Cid spouses initiated a complaint for damages against Philrock and some of its officers and engineers before the Regional Trial Court (RTC) of Quezon City.
    • An Agreement to Arbitrate had been previously executed by the parties, agreeing that their disputes would be resolved by the Construction Industry Arbitration Commission (CIAC).
  • Chronology of Proceedings
    • September 14, 1992 – The Cid spouses file a Complaint for damages in the RTC, Branch 82.
    • December 7, 1993 – The RTC initially dismisses the case and refers it to the CIAC because of the existing arbitration agreement.
    • April 2, 1994 – Disagreements about the scope of arbitration arise regarding whether moral and exemplary damages and tort issues should be included, and whether non-signatory officers and engineers of Philrock should be joined.
    • April 13, 1994 – The CIAC issues an Order dismissing the case and referring it to the RTC due to the unresolved issues between the parties.
    • Subsequent proceedings include:
      • The filing of a Motion to Set Case for Hearing by the Cid spouses at the RTC, opposed by Philrock.
      • June 13, 1995 – The RTC declares it no longer has jurisdiction and orders the case records remanded back to the CIAC.
      • August 21, 1995 – Philrock petitions to suspend the arbitration pending clarification of the RTC’s June 13 Order; however, the CIAC denies the request based on respondent indication to exclude non-consenting parties.
      • Continuation of proceedings leading to the finalization and signing of the Terms of Reference, which encapsulate the identified issues and the dispute parameters.
  • Detailed Factual Developments in Arbitration
    • September 12, 1995 – Philrock files a Motion to Dismiss alleging the CIAC lost jurisdiction due to withdrawal of consent by the respondents.
    • September 22, 1995 – The CIAC denies the Motion to Dismiss.
    • November and February Hearings (1995-1996) – The CIAC instructs the parties to appear and set hearing dates, with specific emphasis on the presentation of evidence and payment of fees.
    • September 24, 1996 – The CIAC delivers its Decision awarding various sums to the Cid spouses for:
      • Excess cash payment for materials ordered (P23,276.25 plus interest at 6% per annum).
      • Retrofitting costs (P65,000.00).
      • Refund for delivered but unworkable concrete (P13,404.54).
      • Moral damages, nominal damages, and attorney’s fees and litigation expenses.
      • Arbitration fees (netted against fees already paid if any).
  • Appellate and Review Proceedings
    • A Petition for Review is subsequently elevated under Rule 45 of the Rules of Court, contesting the CIAC’s jurisdiction and the monetary awards.
    • The Court of Appeals consolidated two cases (CA-GR SP Nos. 39781 and 42443) and upheld:
      • The jurisdiction of the CIAC under Executive Order No. 1008 on disputes arising from construction contracts.
      • The awards rendered by the CIAC based on the substantial evidence on record.
    • The issues raised by Petitioner include arguments on the withdrawal of consent to arbitrate and alleged errors in awarding damages.

Issues:

  • Jurisdiction
    • Whether the CIAC retained jurisdiction over the dispute after the RTC initially dismissed the case and referred it back for arbitration.
    • Whether the withdrawal of consent to arbitrate by one party (as alleged by Petitioner) affected the CIAC’s jurisdiction.
  • Cause of Action
    • Whether the respondent spouses have a proper cause of action against Philrock, despite allegations that any defects were due to respondents’ negligence (failure to secure an engineer or architect).
  • Specific Monetary Awards
    • The propriety of awarding P23,276.25 for excess payment on materials plus the accrual of 6% interest from September 26, 1995.
    • Whether the award of P65,000.00 for retrofitting costs is justified under the circumstances.
    • The legitimacy of awarding P13,404.54 for the refund on delivered but unworkable concrete mix.
  • Award of Moral, Nominal Damages, and Attorney’s Fees
    • Whether awarding moral damages is appropriate given the alleged suffering and lasting impact on the respondents.
    • Whether the grant of nominal damages is proper when actual damages have been proven.
    • Whether Philrock should be held liable for attorney’s fees and litigation expenses incurred by the respondents.
  • Award of Arbitration Fees
    • Whether Petitioner should be responsible for the payment of arbitration fees as determined by the CIAC.

Ruling:

  • (Subscriber-Only)

Ratio:

  • (Subscriber-Only)

Doctrine:

  • (Subscriber-Only)

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster—building context before diving into full texts.