Case Digest (G.R. No. 207257) Core Legal Reasoning Model
Core Legal Reasoning Model
Facts:
In July 2012, 28 public‐interest petitioners (the Casião Group) sought a Writ of Kalikasan before the Supreme Court against respondents Redondo Peninsula Energy, Inc. (RP Energy), Subic Bay Metropolitan Authority (SBMA), and Secretary Paje of the Department of Environment and Natural Resources (DENR). The petition challenged: (1) the December 22, 2008 Environmental Compliance Certificate (ECC) issued by DENR for a 2×150 MW coal‐fired plant in Subic Bay Freeport; (2) two subsequent ECC amendments (July 8, 2010 and May 26, 2011) adding physical components and changing the plant to 1×300 MW; and (3) the June 8, 2010 Lease and Development Agreement (LDA) between SBMA and RP Energy for 38 hectares at Sitio Naglatore. The Casião Group alleged the project would cause acid rain, air and water pollution, health risks and that the ECCs and LDA were invalid for noncompliance with (a) Sections 26–27 of the Local Government Code (no local‐sanggunian approval), (b) Section 59 of the Indigenou Case Digest (G.R. No. 207257) Expanded Legal Reasoning Model
Expanded Legal Reasoning Model
Facts:
- Parties and Agreements
- In 2006, SBMA and Taiwan Cogeneration Corporation (TCC) signed MOUs to build a coal-fired power plant in Subic Bay Industrial Park.
- In 2008, SBMA Ecology Center issued Environmental Compliance Certificate (ECC) No. EC-SBFZ-ECC-69-21-500 to TCC’s subsidiary, TCIC, for a 2×150-MW coal plant at Sitio Naglatore.
- TCC assigned its rights to Redondo Peninsula Energy, Inc. (RP Energy) in June 2008; parties executed an Addendum to the MOU.
- ECC Amendments and Lease Agreement
- RP Energy procured a first ECC amendment (July 8, 2010) to include a barge wharf, breakwater, ash pond, transmission line, etc., submitting an Environmental Performance Report and Management Plan (EPRMP).
- RP Energy procured a second ECC amendment (May 26, 2011) changing the design to 1×300 MW, submitting a Project Description Report (PDR).
- RP Energy applied for a third amendment (September 11, 2012) for a 2×300 MW plant; DENR-EMB issued it on November 15, 2012.
- On June 8, 2010, SBMA and RP Energy entered into a Lease and Development Agreement (LDA) over the 380,004.456 m² project site.
- Writ of Kalikasan Proceedings
- On July 20, 2012, petitioners (the “CasiAo Group”) filed a Petition for Writ of Kalikasan before the Supreme Court, alleging:
- Imminent grave environmental damage and health risks;
- DENR failed to secure prior Sanggunian (LGU) approval under LGC §§ 26–27;
- LDA lacked NCIP Certificate of Non-Overlap under IPRA § 59;
- Section 8.3 of DAO 2003-30 permitting ECC amendments is ultra vires;
- All ECC amendments are null and void.
- The SC issued the writ and referred the case to the CA for hearing.
- The CA (Jan 30, 2013 Decision) denied the writ for lack of proven environmental harm, invalidated the initial ECC and first two amendments for procedural lapses (IPRA, LGC, ECC restrictions), but did not rule on the third amendment.
- CA (May 22, 2013 Resolution) denied all motions for reconsideration.
- Parties filed Petitions for Review on Certiorari before the SC.
Issues:
- Writ of Kalikasan
- Environmental Compliance Certificates
- Lease & Development Agreement
- Miscellaneous
Ruling:
- (Subscriber-Only)
Ratio:
- (Subscriber-Only)
Doctrine:
- (Subscriber-Only)