Facts:
The case revolves around the Manila Electric Company (Meralco) and AAA Cryogenics Philippines, Inc. (AAA) concerning a dispute over power supply fluctuations that significantly affected AAA's operations. AAA, which was engaged in the production of liquid gases like oxygen, nitrogen, and argon, relied heavily on a stable power supply for its processes. Between October 1997 and April 1998, AAA reported various instances of power fluctuations and interruptions, recording specific dates when these incidents occurred. Consequently, AAA calculated the losses resulting from these power issues, amounting to P21,092,760. In communication with Meralco, AAA expressed its concerns over the inconsistent power supply but was advised only to invest in power conditioning equipment to mitigate the effects. Unable to cover its electricity bills, which had reached P13,657,141.56 due to the disruptions, AAA ceased payments, ultimately leading to Meralco disconnecting its service. On April 23, 1998, Case Digest (G.R. No. 207429) Expanded Legal Reasoning Model
Expanded Legal Reasoning Model
Facts:
- Parties and Nature of the Case
- AAA Cryogenics Philippines, Inc. (AAA) is engaged in the production of liquid gases (e.g., liquid oxygen, liquid nitrogen, and liquid argon) which require extremely pure and stable power to maintain the proper operation of its automated plant.
- Manila Electric Company (Meralco), the petitioner, is a public utility company responsible for the supply and distribution of electrical power.
- The dispute arose from alleged power fluctuations and interruptions in the electricity supplied by Meralco, which AAA claimed adversely affected its production processes.
- Operational Background and Critical Dependence on Stable Power
- AAA’s production process is highly computerized, relying on computers and electronic processors that monitor the purity of the liquid gases produced.
- A stable source of power is vital because any fluctuation can cause the plant to shut down, thereby lowering the purity of the product.
- When power fluctuations occur, production losses are incurred due to the need to halt operations (at least four hours to regain adequate purity, and up to 72 hours to “dry out” a frozen plant followed by a 16-hour cooling period).
- Chronology of Power Fluctuations and Interruptions
- Between October 1997 and April 1998, AAA’s Plant Supervisor reported numerous instances of power fluctuations and interruptions as recorded in computer log sheets:
- Specific dates include fluctuations on 10, 14, and 17 October 1997; interruptions on 11 October 1997; and additional irregularities recorded on various dates in November 1997, December 1997, February and March 1998, and finally on 5 April 1998.
- These disturbances led to claimed production losses amounting to P21,092,760.00.
- AAA communicated these issues to Meralco through several letters. In response, Meralco advised AAA to install power conditioning equipment (specifically, a motor generator set) to level out the supply but did not remedy the problem directly.
- Billing and Contractual Breach
- Due to the repeated power issues, AAA stopped paying its electrical bills until its arrears reached P13,657,141.56.
- Meralco, in turn, disconnected service and terminated its contract with AAA.
- After deductions and interest computations, Meralco calculated the unpaid bills at P10,453,477.55.
- Initiation of Legal Actions and Consolidation of Cases
- On 23 April 1998, AAA filed an action for injunction and damages (Civil Case No. 66768) seeking compensation for its alleged losses due to power fluctuations.
- On 16 June 2000, Meralco filed a collection suit (Civil Case No. 67951) to recover its unpaid electrical bills.
- The two cases were consolidated on 9 August 2001 as both arose from the same contract and factual background.
- Evidence Presented at Trial
- AAA submitted computer log sheet readings that recorded the timing of dips in gas purity, which its plant supervisor, Raul D. Cruz, Jr., testified were indicative of power interruptions and fluctuations.
- To quantify its losses, AAA introduced two documentary exhibits:
- "Summary of Production Losses due to Fluctuation"
- "Comparative Presentation of Production under Normal Power Supply, Production when there is Power Fluctuation and Quantity in Cubic Meters of Productive Losses"
- In contrast, Meralco presented two Daily Interruption Reports, prepared by its personnel, which recorded only two incidents of power interruption.
- Meralco’s expert witnesses contended that such fluctuations and interruptions are inherent in electricity supply and therefore normal occurrences.
- Rulings at the Trial and Appellate Levels
- The Regional Trial Court (RTC) in its July 6, 2005 Joint Decision:
- Found Meralco liable for failing to deliver constant energy (in breach of its contractual obligation to deliver energy “at reasonably constant potential and frequency”).
- Awarded AAA P21,092,760.00 as actual damages, plus exemplary damages of P300,000.00 and attorney’s fees of P200,000.00.
- Simultaneously, held AAA liable for its unpaid bills amounting to P10,453,477.55 along with attorney’s fees (20% of that amount).
- Ordered set-off between the parties’ respective liabilities.
- The Court of Appeals (CA):
- Affirmed the RTC’s decision on the occurrence of power fluctuations and interruptions with modifications, notably deleting the award of attorney’s fees for both parties.
- Rejected AAA’s argument against its liability for unpaid bills on the ground that such a defense was not raised previously.
- Held that the evidence (including AAA’s computer recordings confirmed by expert testimony) sufficed to establish the occurrence of power irregularities owed to Meralco’s failure to remedy them.
- Issues Raised in the Petition for Review on Certiorari
- Meralco’s petition challenged:
- The sufficiency and admissibility of evidence establishing the occurrence of power fluctuations and interruptions.
- The basis for awarding actual damages and whether damages could be computed without precise proof of pecuniary loss.
- The propriety of awarding exemplary damages and the deletion of attorney’s fees despite allegations of wanton disregard and financial consequences.
Issues:
- Occurrence and Causation of Power Fluctuations and Interruptions
- Did the power fluctuations and interruptions actually occur as alleged by AAA?
- Were these disturbances attributable to Meralco’s negligence or breach of its contractual duty to provide constant power supply?
- Award of Damages
- Should Meralco be held liable for actual damages when AAA’s proofs of production losses were allegedly based on estimations and not derived from concrete, verifiable evidence?
- Is the award of exemplary damages justified in the absence of proof that Meralco acted in a wanton, fraudulent, reckless, oppressive, or malevolent manner?
- Entitlement to Attorney’s Fees
- Given the circumstances of AAA’s non-payment of its bills and the dispute over performance, is Meralco entitled to recover attorney’s fees?