Title
Ka Kuen Chua vs. Colorite Marketing Corp.
Case
G.R. No. 193969-70
Decision Date
Jul 5, 2017
Dispute over construction delay caused by soil erosion, Hold Order, and shared liability; KKCA ordered to complete project, liquidated damages reduced, and claims for lost rentals denied.

Case Digest (G.R. No. 68969)
Expanded Legal Reasoning Model

Facts:

  • Contract and Project
    • On November 15, 2003, Colorite Marketing Corporation (Colorite) and Architect Ka Kuen Tan Chua doing business as Ka Kuen Chua Architectural (KKCA) signed a contract for KKCA to build a four-storey residential/commercial building on a parcel in Makati City for Php33,000,000.00.
    • Stipulations included:
      • Work to commence within seven days after receiving the Notice to Proceed from Colorite, to be completed within 365 days from the seventh day after a Php6,600,000.00 down payment (20% of the contract price).
      • Liquidated damages of Php10,000.00 per day for delay beyond the completion deadline.
      • A maximum of 73 days (20%) slippage allowed; Colorite could terminate if exceeded.
      • Colorite’s right to take over and complete the project with costs deductible from KKCA’s dues.
    • Additional provisions were incorporated through Addendum #01 and Addendum #02.
    • Excavation subcontracted by Colorite to WE Construction Company (WCC); full blast excavation began January 10, 2004.
  • Incident and Delay
    • On January 17, 2004, excavation caused erosion damaging the adjacent Hontiveros property, prompting a complaint to the Makati City Government.
    • A Hold Order dated January 22, 2004 was issued, stopping excavation and requiring restoration to the damaged property.
    • Restoration of the Hontiveros property completed by October 2005, but the Quitclaim was not secured; thus, the Hold Order remained effective and construction was suspended.
    • Delay grew to 878 days.
  • Claims and Counterclaims
    • Colorite demanded liquidated damages for delay, loss of rental earnings, attorney’s fees, and litigation expenses (Php8,780,000.00 liquidated damages plus Php10,000 per additional day of delay, and Php13,345,481.00 for lost rentals).
    • KKCA disputed claims, refused to pay damages, and argued:
      • Completion period was suspended due to the Hold Order.
      • Colorite failed to pay Soil Protection costs and 70% of restoration of Hontiveros property.
      • Excavation done by the subcontractor, not KKCA.
    • KKCA counterclaimed for soil protection costs, design fees, ECC permit fee, restoration costs, maintenance costs, moral and exemplary damages, and attorney’s fees.
  • Proceedings and Decisions Below
    • The Construction Industry Arbitration Commission (CIAC) issued a Final Award in 2008:
      • Colorite entitled to 50% of liquidated damages claimed, but denied other claims.
      • KKCA partially entitled to soil protection and restoration costs, design fee, denied some claims.
      • Both parties to bear their arbitration costs.
    • Court of Appeals (CA) in 2009 affirmed the award with modifications:
      • Confirmed partial entitlement to liquidated damages for Colorite (50%), denied other claims.
      • KKCA entitled to design fee, partial soil protection claims.
      • Modified award to require Colorite to pay Php550,000.00 of restoration costs (70% share less Php150,000.00 advanced), share maintenance costs, reimburse ECC permit fee to KKCA.
      • KKCA directed to finish the project and secure quitclaim and lifting of Hold Order.
      • Denied moral, exemplary damages, attorney’s fees to both parties.
    • Motions for reconsideration denied; consolidated petitions filed before the Supreme Court.

Issues:

  • Whether KKCA is liable for the delay and payment of liquidated damages and other claims of Colorite.
  • Whether soil protection and excavation works are within KKCA’s contractual responsibility.
  • Whether Colorite is liable to share in the restoration costs of the Hontiveros property.
  • Whether KKCA is obligated to secure the quitclaim and the lifting of the Hold Order to proceed with construction.
  • Whether Colorite is entitled to loss of rental earnings, attorney’s fees, litigation expenses, and exemplary damages.
  • Whether KKCA is entitled to its claims for soil protection costs, design fees, ECC permit fees, moral/exemplary damages, and attorney’s fees.
  • Whether KKCA can be compelled to finish the project despite strained relations and argument against involuntary servitude.
  • Proper amount of liquidated damages considering delay and parties’ respective faults.
  • Proper sharing of increase in construction costs due to delay beyond contract period.

Ruling:

  • (Subscriber-Only)

Ratio:

  • (Subscriber-Only)

Doctrine:

  • (Subscriber-Only)

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster—building context before diving into full texts.