Facts:
This case revolves around a dispute involving the Department of Public Works and Highways (DPWH) as the petitioner and Italian-Thai Development Public Company, Ltd. (ITD) along with Katahira & Engineers International (KEI) as respondents. The conflict originated from a series of contracts and consultancy agreements initiated on March 15, 2002, pertaining to the engineering design and construction supervision of a significant road improvement project in the Philippines. The DPWH appointed a joint venture including KEI and other firms to undertake detailed engineering design tasks, which involved the production of the Engineering Geological and Geohazard Assessment Report (EGGAR). In 2003, DPWH expanded the work scope to accommodate an engineering analysis of the project site’s geological conditions, culminating in a sloping design included in the project bid documents.
However, a shift from the initial sloping design to an "Overhang Design" occurred, agreed upon by
Case Digest (G.R. No. 235853) Expanded Legal Reasoning Model
Facts:
- Formation of the Consultancy Agreement and Project Scope
- On March 15, 2002, the Department of Public Works and Highways (DPWH) and a Joint Venture composed of Katahira & Engineers International (KEI), Pertconsult International, Techniks Group Corporation, Multi-Infra Konsult, Inc., and E.FL Sison Engineers Co. entered into an Agreement for Consultancy Services.
- The Consultancy Agreement covered:
- Detailed engineering design of the Patapat Viaduct, Suyo-Cervantes-Mankayan-Abatan, Cervantes Sabangan, and Ligao-Pio Duran Road Improvement Project under the Arterial Road Links Development Project V (Contract Package IV-A, Suyo-Cervantes Road Section).
- Bidding assistance, construction supervision, environmental compliance monitoring, land acquisition assistance, and coordination with local government units, among other technical services.
- Expansion of Scope and Design Modifications
- In 2003, DPWH and KEI expanded the scope of work through Realignment No. 1 which led to the preparation of the Engineering Geological and Geohazard Assessment Report (EGGAR).
- Key design developments:
- Initial design: KEI as Project Consultant and Engineer created an original sloping design (slope ratios ranging from 0.20:1 to 0.50:1, with a road width between 4.0 and 5.0 meters).
- Abandonment of the original design: With DPWH’s consent, KEI abandoned the original sloping design and imposed an "Overhang Design", which later became a source of dispute.
- Implementation of the Project and Issuance of Variation Orders
- The civil works were divided into sections; separate biddings were conducted for each section. Italian-Thai Development Public Company, Ltd. (ITD) won the bid for rehabilitating and widening the Suyo-Cervantes Road Section.
- On March 27, 2006, ITD and DPWH entered into a Contract Agreement covering:
- Construction of 45.01 kilometers of concrete road.
- Improvements in drainage, construction of slope protection structures, replacement of bridges, and other remedial works.
- Variation Orders altered the project parameters:
- December 17, 2006: Instruction was given by KEI’s Senior Highway Engineer to widen the carriageway uniformly to 6.10 meters and limit stone masonry height to 1.0 meter.
- Subsequent Variation Orders (Nos. 1 through 4) reflected changes such as:
- Shifting from Asphalt Cement Pavement (ACP) to Portland Cement Concrete Pavement (PCCP).
- Standardization of road width with the imposed Overhang Design.
- Addition of Butac Slope Protection and extra slope protection measures, including a catch fence.
- Emergence of the Dispute and Arbitration Proceedings
- In July 2010, ITD submitted its claim for additional compensation for overrun earthwork quantities, attributed to:
- Failures of the overhang design which led to rock collapses, slope failures, and landslides.
- Road realignment activities necessitated by the widened road design.
- Road improvement work amounts that remained unpaid.
- KEI, through a technical report, advocated that ITD’s claims should be denied, leading to:
- A joint survey on 314 cross-sections of the overhang-designed road.
- ITD being officially notified on August 23, 2011, that its additional compensation claims would not be allowed.
- ITD then communicated its intention to initiate arbitration under the Construction Industry Arbitration Commission (CIAC) in September 2011.
- CIAC Final Award and Subsequent Judicial Proceedings
- The CIAC issued a Final Award on January 14, 2014, where it ruled:
- DPWH was liable to pay ITD a net sum of P106,509,724.49, covering overrun earthwork quantities (divided into overhang design-related, road realignment, and road improvement claims) plus legal expenses, subject to adjustments.
- Claims for counterclaims and cross-claims by DPWH and KEI were denied.
- ITD was awarded temperate damages, with interest at 6% per annum until full payment.
- Dissatisfied with the CIAC Award, DPWH elevated the case to the Court of Appeals (CA) by filing a Petition for Review under Rule 43 of the Rules of Court.
- The CA Decision dated November 27, 2017, dismissed the petition, affirming the CIAC award on the basis that the variations and subsequent design implementation economically compelled ITD’s additional excavation works.
- The CA noted that neither DPWH nor KEI disclosed the EGGAR which could have warned ITD about the geological unsuitability for an overhang design.
- Petition for Review Before the Supreme Court
- DPWH elevated the matter before the Supreme Court under Rule 45 of the Rules of Court.
- Grounds raised included alleged grave abuse of discretion by the CA—specifically contending errors in the CIAC’s findings regarding overrun earthwork quantities, application of variation orders, waiver of procedural requirements under FIDIC and COPA, claimant entitlement inconsistencies, and overall damages awarded.
- The Supreme Court’s focus was drawn to the narrow margin for reviewing factual determinations under the arbitration framework, emphasizing that only pure questions of law are amenable to review.
Issues:
- Whether the CIAC and subsequently the CA erred in determining that DPWH was liable for additional overrun earthwork quantities arising from:
- The change from the original sloping design to the overhang design.
- The need for road realignment due to the imposed design modifications (increased road width and limited stone masonry height).
- Additional road improvements and associated miscellaneous works.
- Whether the alleged failure of ITD to strictly comply with the notice requirements under the FIDIC and COPA should bar its claims or constitute grounds for denying its entitlement.
- Whether the CA committed grave abuse of discretion by allowing factual issues to be revisited on appeal, contrary to the strict limitations imposed on reviewing arbitral awards, thereby warranting a relaxation of the Rule 45 requirement to raise only pure questions of law.
Ruling:
- (Subscriber-Only)
Ratio:
- (Subscriber-Only)
Doctrine:
- (Subscriber-Only)