Case Digest (G.R. No. L-21289) Core Legal Reasoning Model
Core Legal Reasoning Model
Facts:
The case involves the petitioners D.M. Wenceslao and Associates, Inc. (WENCESLAO) and Dominador S. Dayrit against the respondent Readycon Trading and Construction Corporation (READYCON). On April 16, 1991, WENCESLAO entered into a contract with READYCON for the purchase of asphalt materials valued at P1,178,308.75 for a project involving the main expressway in the R-1 Toll Project in Parañaque City. The contract stipulated a 20% downpayment of P235,661.75 upon delivery of the materials, with the remaining balance due within fifteen days. WENCESLAO made the downpayment after READYCON delivered asphalt materials worth P1,150,531.75 on April 22, 1991, and READYCON fulfilled its obligation by laying the asphalt on the job site.Fifteen days later, READYCON demanded payment of the remaining balance, but WENCESLAO did not respond to the demand. After sending a demand letter through its counsel on May 30, 1991, and receiving no response, READYCON filed a complaint with the Regional Tr
Case Digest (G.R. No. L-21289) Expanded Legal Reasoning Model
Expanded Legal Reasoning Model
Facts:
- Parties and Background
- Petitioner D.M. Wenceslao and Associates, Inc. (WENCESLAO) is a domestic construction corporation engaged in infrastructure, foundation works, and subdivision development. Its vice-president, Dominador S. Dayrit, is the signatory officer of the company.
- Respondent Readycon Trading and Construction Corporation (READYCON) is equally a domestic corporate entity, primarily engaged in manufacturing and selling asphalt materials.
- Contract Formation and Obligations
- WENCESLAO entered into a contract with the Public Estates Authority (PEA) for the improvement of the main expressway in the R-1 Toll Project along the Coastal Road in Parañaque City. In order to fulfill its contractual obligation to the PEA, WENCESLAO executed a contract with READYCON on April 16, 1991.
- Under the contract with READYCON:
- READYCON agreed to supply asphalt materials valued at P1,178,308.75.
- WENCESLAO was bound to pay a twenty-percent (20%) downpayment (P235,661.75) upon delivery and the remaining balance (P942,647.00) within fifteen (15) days after the delivery of the materials.
- READYCON was further obligated to deliver, lay, roll the asphalt, and, if necessary, perform any corrective work at the jobsite.
- Performance and Breach
- On April 22, 1991, READYCON delivered asphalt materials worth P1,150,531.75, and WENCESLAO duly paid the obligated downpayment of P235,661.75.
- READYCON performed its contractual obligation by laying and rolling the asphalt at the designated jobsite.
- Approximately fifteen (15) days post-performance, READYCON demanded the payment of the balance.
- Despite demand letters and a written demand by READYCON’s counsel on May 30, 1991, WENCESLAO did not pay the remaining balance nor respond to the demands.
- Initiation of Legal Proceedings
- On July 19, 1991, READYCON filed a complaint at the Regional Trial Court (RTC) of Pasig City, Civil Case No. 61159, for collection of a sum of money and damages, and requested a writ of preliminary attachment.
- READYCON complied with procedural requirements by timely posting a bond of P1,150,000, resulting in the RTC Sheriff attaching heavy equipment (asphalt paver, bulldozer, dozer, grader) belonging to WENCESLAO.
- Subsequently, on September 16, 1991, WENCESLAO filed a motion for the release of the attached equipment by posting a counter-bond, which led to their release on September 25, 1991.
- Subsequent Judicial Decisions and Allegations
- On December 26, 1994, the RTC rendered judgment ordering WENCESLAO to pay READYCON P1,014,110.45 (the sum comprising the balance and additional unpaid amounts), with interest at 12% per annum (compounded annually) from August 9, 1991, until full payment, plus attorney’s fees and litigation costs. The counterclaim of WENCESLAO seeking damages for wrongful attachment was dismissed.
- The Court of Appeals affirmed the RTC decision in subsequent rulings (January 30, 2002, and June 20, 2002).
- WENCESLAO contested:
- The interpretation of the contract by claiming it involved not only the sale of materials but also the provision of a service, asserting that the balance should only be payable after the government’s acceptance of READYCON’s work.
- The occurrence of wrongful and damaging attachment of its heavy equipment, stating that the attachment caused considerable losses (a claimed loss of P1.9 million over 19 days, additional expenses for pullout and repair).
- READYCON, in its defense, maintained that the issuance of the writ was properly executed under the law—with no finding of malice or bad faith—and that WENCESLAO’s own inaction (i.e., failure to respond to demands or promptly file a counter-bond) was the cause of any alleged damage.
Issues:
- Issues on Damages Arising from the Writ of Preliminary Attachment
- Whether READYCON is liable to pay actual or compensatory damages to WENCESLAO for the alleged wrongful issuance and enforcement of the writ of preliminary attachment.
- Whether the posting of a counter-bond by WENCESLAO constitutes a waiver of the right to claim damages arising from the attachment.
- Issues on the Due and Demandable Nature of the Balance Payment
- Whether WENCESLAO’s obligation to pay the balance under the contract was already due and demandable as of May 30, 1991, when READYCON made its demand.
- Whether the contract implied that the balance was payable only upon the government's acceptance of the work, despite the explicit contractual term of payment within fifteen (15) days after delivery.
- Issue on the Nature of the Review
- Whether the appeal by certiorari raised questions of fact or solely errors in law regarding the interpretation of the contract and the propriety of the writ.
Ruling:
- (Subscriber-Only)
Ratio:
- (Subscriber-Only)
Doctrine:
- (Subscriber-Only)