Title
BF Corp. vs. Court of Appeals
Case
G.R. No. 120105
Decision Date
Mar 27, 1998
Construction dispute between BF Corp and SPI over EDSA Plaza Project; arbitration clause upheld, court proceedings suspended pending arbitration.
A

Case Digest (G.R. No. 96161)

Facts:

  • Parties and Initial Agreements
    • BF Corporation (contractor) and Shangri-La Properties, Inc. (SPI, owner) entered into a First Agreement for the construction of the main structure of the EDSA Plaza Project, a shopping mall complex in Mandaluyong City.
    • On November 30, 1990, a fire damaged Phase I of the project. To address the damage and extend work, the parties negotiated a revised contract.
  • May 30, 1991 Agreement for Builder’s Work
    • The parties executed a written “Agreement for the Execution of Builder’s Work for the EDSA Plaza Project,” covering work from May 1, 1991 until completion.
    • The Agreement provided for progress billing, final payment provisions, liquidated damages for delay (P 80,000/day up to 5% of contract price), and—by reference to the “Conditions of Contract”—an arbitration clause for disputes.
  • Emergence of Dispute and Trial Court Proceedings
    • SPI alleged BF incurred serious delays and abandoned the project; BF claimed faithful performance post-fire.
    • July 12, 1993: Parties’ representatives met in conference to settle liabilities—no agreement reached.
    • July 14, 1993: BF filed a collection complaint (RTC Pasig) for unpaid balance (~P 110,883,101.52) against SPI and its board members.
    • August 3–4, 1993: SPI moved to suspend proceedings, invoking arbitration clause; attached contract documents (Articles of Agreement and Conditions of Contract).
    • BF opposed, denying the existence of any arbitration clause; RTC denied the motion to suspend, finding the clause not duly signed or binding and, in any event, invoked too late.
  • Appellate Proceedings
    • SPI sought certiorari under Rule 65 before the Court of Appeals (CA).
    • CA granted the petition, held the arbitration clause validly incorporated and timely invoked (demand made Aug. 13, 1993), annulled RTC orders, and stayed proceedings.
    • BF elevated to the Supreme Court by petition for review on certiorari.

Issues:

  • Does the May 30, 1991 contract embody a valid and binding arbitration clause?
  • If so, was SPI’s invocation of arbitration timely under the contract’s “reasonable time” requirement?
  • Was resort to certiorari proper to review the RTC’s denial of the motion to stay proceedings, or should SPI have appealed?

Ruling:

  • (Subscriber-Only)

Ratio:

  • (Subscriber-Only)

Doctrine:

  • (Subscriber-Only)

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.