Title
Continental Cement Corp. vs. Asea Brown Boveri, Inc.
Case
G.R. No. 171660
Decision Date
Oct 17, 2011
CCC sued ABB for breach of contract after repeated motor repair failures, claiming damages. SC ruled ABB liable for penalties but denied production loss claims, citing lack of foreseeability and insufficient evidence.

Case Summary (G.R. No. 171660)

Key Dates and Contractual Terms

Delivery of motor to respondents for repair: July 11, 1990 (PO Nos. 17136–17137). Down payment: July 18, 1990. Delivery date stipulated: August 29, 1990 (six weeks). Penalty clause: 0.5% of total cost per day (P987.25/day). Tests and failures: October 3–4, 1990 (first test failed), November 14–19, 1990 (second), March 13–15, 1991 (third). Motor actually delivered to petitioner: January 7, 1991. Complaint filed: October 23, 1991.

Factual Background

CCC contracted ABB (and BBC, with ABB as surviving entity) to repair a 160 KW Kiln DC Drive Motor. Repeated repair attempts allegedly failed, causing several operational interruptions and claimed production losses. CCC sued the corporations and Eriksson personally, seeking declared production and opportunity losses (P10,600,000), labor and crane rental (P26,965.78), contractual penalties (P331,716 claimed), interest, and attorney’s fees.

Contractual Clause in Dispute (Clause 7)

ABB relied on Clause 7 of its General Conditions appended to its letter of offer, which limited liability to defects within the guarantee period and expressly excluded consequential loss, expenses for repairs made without written authority, and other indirect damages. ABB asserted that CCC accepted these General Conditions by issuing the purchase orders.

Procedural History and Lower Court Rulings

RTC (Branch 101, Quezon City) rendered judgment for CCC, awarding production loss (P10,600,000), labor/crane rental (P26,965.78), and attorney’s fees (P100,000). The CA reversed and dismissed the complaint, giving effect to Clause 7 and reasoning that no implied warranty arises on repair work; thus, respondents could not be held for consequential production losses. CCC sought Supreme Court review by petition for certiorari.

Issues Presented to the Supreme Court

Primary issues: (1) whether the CA erred in applying the General Conditions (Clause 7) to exculpate respondents from liability; (2) whether the CA erred in applying doctrines of implied warranty and warranty against hidden defects to absolve respondents from contractual obligations; and (3) the proper measure of recovery, including penalties, consequential damages, attorney’s fees, and possible personal liability of Eriksson.

Standard for Incorporation of Contractual Terms

The Supreme Court held that Clause 7 is not binding on CCC because respondents failed to prove that CCC was furnished a copy of the General Conditions. A contractual term that limits liability must be shown to have been communicated and accepted; absent proof of such notice or incorporation, the limiting clause cannot be invoked against the party who never received it.

Liability under the Civil Code for Failure to Perform

The Court applied Articles 1167 and 1170 of the Civil Code: obligation unperformed must be executed at the obligor’s cost, and those guilty of negligence or delay are liable for damages. Article 2201 governs foreseeability of consequential damages in contracts and quasi-contracts. The Court concluded a repairman who fails to perform is liable for execution cost and damages that are natural and probable consequences of breach.

Application to Penalty Clause (Article 1226)

Article 1226 was held applicable: in obligations with a penal clause, the penalty substitutes indemnity for damages and interest unless otherwise stipulated. Where the penalty is demandable, it covers other damages claimed (production loss, labor, crane rental) unless the obligor refuses to pay the penalty or is guilty of fraud. The Court found CCC entitled to enforce the penalty provision at P987.25 per day for delay.

Computation and Temporal Scope of Penalties

Although testing occurred on March 13, 1991, the motor had been delivered to CCC on January 7, 1991; installation and testing were postponed at CCC’s request due to kiln repairs. Consequently, the Court computed the penalty from August 30, 1990 (start of delay) up to January 7, 1991 (delivery date) — a period of 131 days — resulting in P129,329.75 as the proper penalty award.

Denial of Additional Damages for Production Loss, Labor, and Crane Rental

The Court denied CCC’s claims for production loss and for labor/crane rental beyond the penalty award. Reasons: (1) lack of competent proof — CCC failed to present production reports covering August 1990 to March 1991 (only April–June 1990 reports were offered), so alleged production losses could not be established with reasonable certainty; (2) consequential damages require that such losses be reasonably foreseen or within the parties’ contemplation when contracting; given the repair involved a spare motor, ABB could

...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.