Title
Bosque vs. Yu Chipco
Case
G.R. No. 3862
Decision Date
Sep 6, 1909
Contract dispute over house construction; both parties failed obligations. Court absolved liability, denied damages for typhoon destruction, balancing claims.
Font Size:

Case Digest (G.R. No. 3862)

Facts:

    Contract Formation and Obligations

    • On or about August 1, 1905, the plaintiff and defendant entered into a contract whereby the defendant was to construct a house for the plaintiff.
    • The contract stipulated that the construction be completed within four months after its signing and delivery; the payment schedule required four equal payments tied to the state of completion of the construction.

    Modifications and Additional Work

    • The plaintiff made changes and additions to the original plans, which were subsequently agreed upon by the defendant.
    • A new contract was executed to incorporate these modifications.
    • The plaintiff failed to secure the necessary permit from the city authorities in Manila for the additions, consequently delaying the defendant’s work for several weeks.

    Performance and Payment Issues

    • Construction commenced under the original contract, and the house had reached a state of completion that warranted the first payment; however, the plaintiff did not make any payment under either the original or modified contract.
    • The defendant alleged that the plaintiff’s failure to make timely payments hindered his ability to continue construction.
    • The plaintiff furnished various pieces of timber to the defendant, valued at P132, which were used in the building process.
    • The defendant proved that he had expended P500 in labor and material for the additions made to the house.
    • A dispute arose as to whether the materials supplied conformed to the contractual terms, with the defendant’s witnesses testifying that the materials were consistent with what had been agreed upon.

    Events Leading to Litigation

    • Prior to the completion of the house, a heavy bagui (a strong windstorm) destroyed the structure.
    • On December 19, 1906, the plaintiff initiated an action against the defendant seeking:
    • Recovery of P132 for the timber supplied.
    • P600 in damages for the defendant's failure to complete the construction within the contracted four-month period.
    • The defendant, in his answer, denied the allegations, detailed the existence of both the original and new contracts, and counterclaimed for a judgment against the plaintiff amounting to P1,928.56 based on failure of payment.

    Lower Court’s Findings and Judgment

    • The lower court observed that both parties had failed to fully perform their respective contractual obligations.
    • It was determined that:
    • The plaintiff had used materials to the defendant’s benefit, entitling him to recover P132.
    • The defendant had incurred expenses of P500 for additional work per the plaintiff’s direction; hence, he was entitled to recover this amount from the plaintiff.
    • By balancing the mutual breaches, the lower court awarded a net judgment in favor of the defendant:
    • The defendant was to recover P368 from the plaintiff, which was the difference between his expenditure (P500) and the value of materials provided (P132).

    Appeal and Contentions Raised

    • The plaintiff appealed the lower court’s judgment, citing provisions of Articles 1124 and 1591 of the Civil Code.
    • The appellant argued:
    • The court erred by not absolving both parties from further liability under the contract.
    • The defendant, as the contractor, should be held liable for the loss and damage incurred from the building’s destruction.

Issue:

    Whether the lower court erred by not explicitly declaring the parties absolved from any further obligations under the contract pursuant to Article 1124 of the Civil Code.

    • Whether the failure of both parties to perform their respective contractual duties automatically resulted in their mutual discharge.

    Whether the evidence supported the plaintiff’s claim for additional damages, including the alleged P600 for delay and the claim against the defendant for the destruction of the house by a baguio.

    • Whether the destruction of the house was due to the defendant’s negligence or defects in construction warranting further liability.
  • Whether the netting-off of amounts (i.e., awarding the defendant P368 as the difference between the amount spent and the value of material supplied) was the proper remedy given the mutual non-performance.

Ruling:

  • (Subscriber-Only)

Ratio:

  • (Subscriber-Only)

Doctrine:

  • (Subscriber-Only)

Analyze Cases Smarter, Faster
Jur is an AI-powered legal research platform in the Philippines for case digests, summaries, and jurisprudence. AI-generated content may contain inaccuracies; please verify independently.