Atlantic, Gulf and Pacific Co. vs. Government of the Philippine Islands
Case
G.R. No. L-4195
Decision Date
Feb 18, 1908
Contractor repaired initial bulkhead damage; typhoon caused further damage; court ruled contractor liable for typhoon’s external pressure per contract terms.
Font Size:

Case Digest (G.R. No. L-4195)

Facts:

    Parties and Contract Formation

    • The plaintiff, The Atlantic, Gulf and Pacific Company, contracted with a representative of the defendant, the Government of the Philippine Islands, to undertake improvements on the Luneta Extension in Manila.
    • The work involved constructing a rock and timber bulkhead, dredging and filling a space with up to 400,000 cubic yards of material, and building foundations for both the extension and a lighthouse.
    • Specific contract provisions included detailed clauses regarding the reinforcement of the timber bulkhead, the responsibilities for damage repairs, and a mechanism for deducting losses of dredged materials.

    Contract Clauses and Allocation of Risk

    • Clause 4 required that the timber bulkhead be reinforced with a riprap revetment deployed to protect it against mud fill pressures.
    • Clause 5 stipulated that the contractor would be responsible for all damages arising from wave action or from the pressure of the revetment against the timber structure. However, if a break was caused by pressure from the mud fill, repairs would be paid by the Government, provided that the contract specifications were fully met.
    • Clause 12 provided a method for measuring losses of dredged materials, subtracting these from the final payment.

    The Incident Sequence

    • On May 1, 1906, while the improvements were in the agreed condition, approximately 200 feet of the bulkhead and its revetment became displaced due to the internal pressure of the mud fill. This displacement allowed a considerable amount of fill to escape into the bay.
    • Following the break, the plaintiff commenced repair work based on directions from the Government’s representative.
    • On May 18-19, 1906, a severe typhoon struck Manila. By that time, the break had not been adequately repaired, leading to further, extensive damage when the unsupported bulkhead and revetment succumbed to the force of wind and wave action.
    • The additional force of the typhoon, combined with the already compromised condition due to the prior escape of fill, resulted in damage over a distance of approximately 1,800 feet and an even greater loss of fill material.

    Subsequent Supplementary Contract and Communications

    • On May 24, 1906, a supplementary contract was entered into by the same parties. This agreement recited the events of May 1 and modified the method of repair:
- Repairs were to be accomplished by filling the gap with stone and other materials, followed by the erection of a temporary timber bulkhead. - The Government agreed to pay the actual and reasonable cost of the repairs plus an additional 15 percent.

    Contextual and Legal Framework

    • The contract and its stipulated clauses clearly allocated responsibility between the parties:
- The Government assumed responsibility for repair costs stemming from internal pressure-induced breaks. - The contractor was expressly responsible for damages incurred from external forces (e.g., wave action, typhoon effects).

Issue:

    Determination of Liability for Typhoon Damage

    • Who bears the responsibility for the extensive damage resulting from the typhoon of May 18-19, given that the structure had already been compromised by the break on May 1?
    • Does the contractual language and supplementary agreement shift the burden of loss for typhoon-induced damage exclusively onto the contractor despite the concurrent occurrence of the natural disaster?

    Interpretation of Contractual Provisions

    • Whether the specific clauses in the contract sufficiently allocate the risk of damage between internal and external causes (i.e., pressure from within versus damage from typhoon and wave action).
    • How should the “proximate cause” of the damage be determined when there is an intervening event (the typhoon) following an initial failure due to internal pressure?

    Effect of the Supplementary Contract

    • Does the supplementary agreement, which clearly delineates the quantities and methods required for repair after the May 1 break, serve as a settlement of all claims related to the earlier damage?
    • Is the subsequent claim by the plaintiff that the Government should be liable for typhoon damage properly supported given the acts and agreements of the parties immediately following the initial break?

Ruling:

  • (Subscriber-Only)

Ratio:

  • (Subscriber-Only)

Doctrine:

  • (Subscriber-Only)