Title
Ang Toa vs. Alvarez
Case
G.R. No. 4390
Decision Date
Aug 24, 1908
Plaintiff claims unpaid contract price for building construction; defendants counterclaim for defects. Court rules acceptance under protest doesn’t waive damages, affirms judgment for plaintiff minus defect costs.
Font Size:

Case Digest (G.R. No. 4390)

Facts:

    The Contract and Construction Agreement

    • The plaintiff, Ang Toa, entered into a contractual agreement to erect a building for the defendants.
    • The original complaint alleged that the plaintiff had duly completed all work required by the written contract and that the work was finished as of January 21, 1907.
    • It was further alleged that the defendants had paid only a part of the agreed contract price.
    • Notably, the original complaint did not allege delivery or acceptance of the property by the defendants nor did it mention any extra work performed.

    The Amended Complaint and Stipulated Agreement

    • On August 26, 1907, the plaintiff filed an amended complaint, which was accepted by the defendants under certain stipulations.
    • The agreement included:
    • That the answer to the original complaint would be considered as the answer to the amended complaint.
    • That Exhibits A and B attached originally would also be deemed part of the amended complaint.
    • That the defendants agreed to the truthfulness of the allegations in the amended complaint, except for the additional work claim stating that extra labor performed entitled the plaintiff to additional compensation.
    • The amended complaint introduced the allegation that additional work was performed by the plaintiff amounting to a value of P190, and it asserted that the defendants had accepted the building by taking possession and using it.

    Evidence Presented and Trial Proceedings

    • During trial, the plaintiff provided evidence of not only the execution of the original contract but also proof of additional work performed.
    • Evidence was submitted showing the delivery of the building, its acceptance by the defendants, and subsequent occupation and use, although such acceptance was later contested as being conditional and under protest.
    • Defendants Martinez and Basilia Alvarez denied that the plaintiff had fully complied with the contractual terms.
    • In her counterclaim, Basilia Alvarez provided detailed allegations of the plaintiff’s non-compliance with specific contract specifications, estimating a reconstruction cost of P1,500.
    • The trial court found that:
    • P1,990 of the contract price remained unpaid.
    • Extra labor and materials valued at P170 were indeed performed by the plaintiff.
    • Evidence supporting the defendants’ counterclaim showed that materials valued at P440 were substandard, leading the court to order judgment against the defendants for P1,550.
    • Throughout the proceedings, the plaintiff did not object to the introduction of evidence supporting the counterclaim, despite his later contention that such evidence should have been excluded under the stipulation.

    Parties’ Conduct and Subsequent Understanding

    • The court’s initial broad statement regarding the amended complaint and acceptance of evidence was not interpreted by any party as a waiver of any right, including the counterclaim.
    • The plaintiff’s continuous effort to prove both the delivery/acceptance of the building and the additional work performed indicates he did not believe in, nor relied on, any waiver of the counterclaim.
    • Similarly, the defendants introduced evidence regarding their counterclaim without any suggestion that the prior stipulation had relinquished that right.
    • The judge’s ultimate findings confirm that all parties and the court understood the stipulation in its broad context rather than as a waiver of material issues.

Issue:

    Whether the stipulation accompanying the filing of the amended complaint amounted to a waiver by the defendants of their right to assert a counterclaim.

    • Did the agreement that the answer to the original complaint would serve as the answer to the amended complaint also preclude the introduction of evidence pertaining to the counterclaim?
    • Was the subsequent submission and admission of evidence on the counterclaim affected by such a stipulation?

    The Effect of Delivery and Acceptance

    • Whether the presentation of evidence regarding the delivery of the building to, and its acceptance by, the defendants constituted a waiver of the counterclaim by mere occupation and usage.
    • Whether the conditional or protest nature of the acceptance by the defendants negated any implied waiver.

    The Role of Party Conduct and Judicial Interpretation

    • Whether the conduct of the parties during the trial, particularly the lack of objection to evidence related to the counterclaim, implies a waiver or is merely procedural compliance.
    • Whether the judge’s interpretation of the broad stipulation was consistent with the parties’ conduct and the overall evidence presented.

Ruling:

  • (Subscriber-Only)

Ratio:

  • (Subscriber-Only)

Doctrine:

  • (Subscriber-Only)

Analyze Cases Smarter, Faster
Jur is an AI-powered legal research platform in the Philippines for case digests, summaries, and jurisprudence. AI-generated content may contain inaccuracies; please verify independently.